Mazar - Sharif


There are 4 Priority Projects and 5 Emergency Projects in Mazar-e-Sharif. Please see the table and map below for details. Note that additional projects are in the pipeline for implementation. Please see the jobs/contracts page for details on projects for which there is currently an invitation to tender.


Priority Projects


ID

Intervention type

Status

Cost (USD)

Completion date

Estimated beneficiaries

Sub-project description

Road figures

MZR-PP-08

Road/Street Upgrading and Drainage

Completed

207,988.00

13 March 2021

22,206

Construction of Ota Qul & Ghulam Sakhi Khan Bagh Asphalt Streets in District 3

0.8170 KM

MZR-PP-26

Road/Street Upgrading and Drainage

Completed

352,064.13

15 February 2021

12,150

Construction of Kart -e-Sulh 3 Asphalt Road in District 7

0.5550 KM

MZR-PP-23

Road/Street Upgrading and Drainage

Completed

639,226.05

13 March 2021

32,400

Construction of Baba Yadgar Tertiary Road in District 4

1.6149 KM

MZR-PP-27

Road/Street Upgrading and Drainage

Completed

216,284.11

15 February 2021

10,800

Construction of North of Amani Project's Asphalt Road in District 7

0.5770 KM


Emergency Projects


 

ID

Intervention type

Status

Cost (USD)

Complete date

Estimated labor days

Sub-project description

Road figures

Drain/Canal figures

MZR-CRP-01

Road median leveling

Completed

42,342.00

 ---

                    3,763.73

Road Median Leveling and cearing project

5.6 KM

0 KM

MZR-CRP-04

Canal cleaning

Completed

59,942.00

 ---

                    5,328.18

Nahre Shahy Canal Cleaning project

0 KM

4 KM

MZR-CRP-05

Drain cleaning

Completed

7,948.20

 ---

                       706.51

Drain Cleaning project

0 KM

6 KM

MZR-CRP-06

Drain cleaning

Completed

18,377.00

 ---

                    1,633.51

Drain Cleaning project

0 KM

14 KM

MZR-CRP-07

Road median leveling

Completed

19,315.00

 ---

                    1,716.89

Road Median Leveling project

2.5 KM

0 KM